Hello everyone, There's plenty of time before the release process starts, but I'd like to begin the schedule discussion. For the September release we usually branch mid-July. However, this year my vacation runs a little later, so a good branch date for me would be the 1st of August. Proposal: - 1 August 2018: Branch; RC1 soon after - 22 August 2018: RC2; all lose ends should be tied up by now - 5 September; final tag, release a few days later (don't slip past first half of September) What do you think? I'm particularly keen to hear from those helping to test the release, and from downstream consumers of the branch. If the community prefers an earlier branch date, I can take a day off vacation to set it up but I probably can't help much with bug fixing and merging before August. Thanks, Hans
> Proposal: > > - 1 August 2018: Branch; RC1 soon after > - 22 August 2018: RC2; all lose ends should be tied up by now > - 5 September; final tag, release a few days later (don't slip past > first half of September) > > What do you think? > > I'm particularly keen to hear from those helping to test the release, > and from downstream consumers of the branch.As a downstream consumer, Sony is okay with the proposed schedule. --paulr
Somchai Smythe via llvm-dev
2018-Jun-08 03:34 UTC
[llvm-dev] [7.0.0 Release] Schedule proposal
I think you need to get 6.0.1 out the door first.... On 6/7/18, Hans Wennborg via llvm-dev <llvm-dev at lists.llvm.org> wrote:> Hello everyone, > > There's plenty of time before the release process starts, but I'd like > to begin the schedule discussion. > > For the September release we usually branch mid-July. However, this > year my vacation runs a little later, so a good branch date for me > would be the 1st of August. > > Proposal: > > - 1 August 2018: Branch; RC1 soon after > - 22 August 2018: RC2; all lose ends should be tied up by now > - 5 September; final tag, release a few days later (don't slip past > first half of September) > > What do you think? > > I'm particularly keen to hear from those helping to test the release, > and from downstream consumers of the branch. > > If the community prefers an earlier branch date, I can take a day off > vacation to set it up but I probably can't help much with bug fixing > and merging before August. > > Thanks, > Hans > _______________________________________________ > LLVM Developers mailing list > llvm-dev at lists.llvm.org > http://lists.llvm.org/cgi-bin/mailman/listinfo/llvm-dev >
Hans Wennborg via llvm-dev
2018-Jun-08 07:32 UTC
[llvm-dev] [7.0.0 Release] Schedule proposal
Yes, I expect that to have happened well before this process starts. On Fri, Jun 8, 2018 at 5:34 AM, Somchai Smythe <buraphalinuxserver at gmail.com> wrote:> I think you need to get 6.0.1 out the door first.... > > On 6/7/18, Hans Wennborg via llvm-dev <llvm-dev at lists.llvm.org> wrote: >> Hello everyone, >> >> There's plenty of time before the release process starts, but I'd like >> to begin the schedule discussion. >> >> For the September release we usually branch mid-July. However, this >> year my vacation runs a little later, so a good branch date for me >> would be the 1st of August. >> >> Proposal: >> >> - 1 August 2018: Branch; RC1 soon after >> - 22 August 2018: RC2; all lose ends should be tied up by now >> - 5 September; final tag, release a few days later (don't slip past >> first half of September) >> >> What do you think? >> >> I'm particularly keen to hear from those helping to test the release, >> and from downstream consumers of the branch. >> >> If the community prefers an earlier branch date, I can take a day off >> vacation to set it up but I probably can't help much with bug fixing >> and merging before August. >> >> Thanks, >> Hans >> _______________________________________________ >> LLVM Developers mailing list >> llvm-dev at lists.llvm.org >> http://lists.llvm.org/cgi-bin/mailman/listinfo/llvm-dev >>
Hans Wennborg via llvm-dev
2018-Jun-12 08:37 UTC
[llvm-dev] [cfe-dev] [7.0.0 Release] Schedule proposal
On Thu, Jun 7, 2018 at 6:56 PM, <paul.robinson at sony.com> wrote:>> Proposal: >> >> - 1 August 2018: Branch; RC1 soon after >> - 22 August 2018: RC2; all lose ends should be tied up by now >> - 5 September; final tag, release a few days later (don't slip past >> first half of September) >> >> What do you think? >> >> I'm particularly keen to hear from those helping to test the release, >> and from downstream consumers of the branch. > > As a downstream consumer, Sony is okay with the proposed schedule. > --paulrThanks! I've added the schedule to the website. - Hans