[llvm-dev] [6.0.0 Release] Scheduling the release
Hello everyone, It's time to start making plans for the 6.0.0 release. Following our regular schedule, the branch would occur about two weeks into January, on Wednesday 17 January 2018, with the goal of shipping early March. This is the schedule I would propose. However, one large consumer of the branch has asked if we could start earlier this time, branching on 3 January instead (not moving the ship date), to get a longer period for stabilization that syncs with their internal process. While I'm hesitant to change the schedule because I think it's important that it's predictable, there is a benefit of having large users "in sync" with the upstream release branch, as that means more people testing the same code. I will be out of the office the first weeks of January (and I'm guessing other members of the community might be too), so while I could get the branch started on the 3rd, it would be a kind of "slow-start" of the process, but still allow those who want to start testing and nominating merges to do so. Ultimately, it comes down to what the community prefers. Should we stick to the regular schedule, or should we do the "slow-start" two weeks early this time? Let me know what you think, especially those of you involved in the release testing. Cheers, Hans
Robinson, Paul via llvm-dev
2017-Dec-06 21:06 UTC
[llvm-dev] [lldb-dev] [6.0.0 Release] Scheduling the release
> -----Original Message----- > From: lldb-dev [mailto:lldb-dev-bounces at lists.llvm.org] On Behalf Of Hans > Wennborg via lldb-dev > Sent: Wednesday, December 06, 2017 9:29 AM > To: Release-testers; llvm-dev; cfe-dev; LLDB Dev; openmp-dev (openmp- > dev at lists.llvm.org) > Subject: [lldb-dev] [6.0.0 Release] Scheduling the release > > Hello everyone, > > It's time to start making plans for the 6.0.0 release. > > Following our regular schedule, the branch would occur about two weeks > into January, on Wednesday 17 January 2018, with the goal of shipping > early March. This is the schedule I would propose. > > However, one large consumer of the branch has asked if we could start > earlier this time, branching on 3 January instead (not moving the ship > date), to get a longer period for stabilization that syncs with their > internal process.I'm very sympathetic to syncing upstream stabilization with internal processes; that said, branching so soon after New Year's Day (which I'd guess is celebrated essentially everywhere) seems like not such a great idea. This is not a strong objection, more of an observation. Can I make a counter-offer of Monday, 8 January? If that's a real problem, then we can live with 3 January. --paulr> > While I'm hesitant to change the schedule because I think it's > important that it's predictable, there is a benefit of having large > users "in sync" with the upstream release branch, as that means more > people testing the same code. > > I will be out of the office the first weeks of January (and I'm > guessing other members of the community might be too), so while I > could get the branch started on the 3rd, it would be a kind of > "slow-start" of the process, but still allow those who want to start > testing and nominating merges to do so. > > Ultimately, it comes down to what the community prefers. Should we > stick to the regular schedule, or should we do the "slow-start" two > weeks early this time? > > Let me know what you think, especially those of you involved in the > release testing. > > Cheers, > Hans > _______________________________________________ > lldb-dev mailing list > lldb-dev at lists.llvm.org > http://lists.llvm.org/cgi-bin/mailman/listinfo/lldb-dev
Dimitry Andric via llvm-dev
2017-Dec-07 11:30 UTC
[llvm-dev] [cfe-dev] [6.0.0 Release] Scheduling the release
On 6 Dec 2017, at 18:28, Hans Wennborg via cfe-dev <cfe-dev at lists.llvm.org> wrote:> > It's time to start making plans for the 6.0.0 release. > > Following our regular schedule, the branch would occur about two weeks > into January, on Wednesday 17 January 2018, with the goal of shipping > early March. This is the schedule I would propose. > > However, one large consumer of the branch has asked if we could start > earlier this time, branching on 3 January instead (not moving the ship > date), to get a longer period for stabilization that syncs with their > internal process.I have a few remarks. 1) We are still busy with the 5.0.1 release, and this next (major) branching is pretty soon afterwards. Please make sure not to burn out your testers. :) 2) I would really like some sort of stabilization to take place *before* major branching occurs. (In FreeBSD land, we call this the "slush" period.) By now, it should be well-known when such major branching happens, e.g. somewhere at the start of the year, and somewhere in the middle. So people should start stabilizing, say, one or two months in advance of that. Which means to postpone huge restructuring efforts, or adding big new untested features, but concentrate on fixing bugs, ensuring test cases succeed on all platforms, and generally getting the tree in "good shape". It would be nice if the release manager(s) sent a reminder about this well in advance of the actual branch date, explicitly mentioning the desire to stabilize. Maybe mails like this could be used for such reminders. Having said all that, for me branching earlier is not a problem. For corporate contributors it would maybe be a bit soon after the holiday season... :) -Dimitry -------------- next part -------------- A non-text attachment was scrubbed... Name: signature.asc Type: application/pgp-signature Size: 223 bytes Desc: Message signed with OpenPGP URL: <http://lists.llvm.org/pipermail/llvm-dev/attachments/20171207/bddaf576/attachment.sig>
Renato Golin via llvm-dev
2017-Dec-07 19:50 UTC
[llvm-dev] [6.0.0 Release] Scheduling the release
On 6 December 2017 at 17:28, Hans Wennborg via llvm-dev <llvm-dev at lists.llvm.org> wrote:> However, one large consumer of the branch has asked if we could start > earlier this time, branching on 3 January instead (not moving the ship > date), to get a longer period for stabilization that syncs with their > internal process.Hi Hans, I see this as a positive move. As most people prepare to go into end-of-year mode, they take less risks and commit less experimental code. After the year begins again, people start taking more risks. The closer we branch to the beginning of the year, they less experimental half-backed stuff we'll carry on to the new branch and the less reverts we'll have to do. Well, that's the theory. I don't have strong arguments to back that up, it's just a feeling, but being 3rd as random as 17th, it makes no big difference.> While I'm hesitant to change the schedule because I think it's > important that it's predictable, there is a benefit of having large > users "in sync" with the upstream release branch, as that means more > people testing the same code.Predictability is important when it happens for a reason. Just because it was the same last year is a weak argument to begin with. If we have a better one (helps stabilisation), then I can't see why we should stick to whatever random date we had before.> Ultimately, it comes down to what the community prefers. Should we > stick to the regular schedule, or should we do the "slow-start" two > weeks early this time?As Dimitry said, this can work nicely as a feature-freeze period, like BSD and GCC. We don't have to change anything on our side, as we'll continue to propose patches to backport, but having a longer start means we can backport more fixes before RC1 is marked and have higher chances that it will be stable. Our internal process is easy enough (Jenkins based, little manual work) that it doesn't matter much when we do. What consumes most of the work is the bugs that we find and have to backport a fix, so if we do anything to improve that, and a longer stabilisation period helps, then I support this change. cheers, --renato
Renato Golin via llvm-dev
2017-Dec-07 19:52 UTC
[llvm-dev] [lldb-dev] [6.0.0 Release] Scheduling the release
On 6 December 2017 at 21:06, Robinson, Paul via llvm-dev <llvm-dev at lists.llvm.org> wrote:> I'm very sympathetic to syncing upstream stabilization with internal > processes; that said, branching so soon after New Year's Day (which > I'd guess is celebrated essentially everywhere) seems like not such a > great idea. This is not a strong objection, more of an observation.Hi Paul, I'm curious as to what problems you're expecting... My reasoning (more of a feeling) is that most people will refrain from controversial changes just before the turn of the year, though I have no data points to corroborate that. :) cheers, --renato
Tom Stellard via llvm-dev
2017-Dec-07 20:55 UTC
[llvm-dev] [cfe-dev] [6.0.0 Release] Scheduling the release
On 12/06/2017 09:28 AM, Hans Wennborg via cfe-dev wrote:> Hello everyone, > > It's time to start making plans for the 6.0.0 release. > > Following our regular schedule, the branch would occur about two weeks > into January, on Wednesday 17 January 2018, with the goal of shipping > early March. This is the schedule I would propose. > > However, one large consumer of the branch has asked if we could start > earlier this time, branching on 3 January instead (not moving the ship > date), to get a longer period for stabilization that syncs with their > internal process. > > While I'm hesitant to change the schedule because I think it's > important that it's predictable, there is a benefit of having large > users "in sync" with the upstream release branch, as that means more > people testing the same code. > > I will be out of the office the first weeks of January (and I'm > guessing other members of the community might be too), so while I > could get the branch started on the 3rd, it would be a kind of > "slow-start" of the process, but still allow those who want to start > testing and nominating merges to do so. > > Ultimately, it comes down to what the community prefers. Should we > stick to the regular schedule, or should we do the "slow-start" two > weeks early this time? > > Let me know what you think, especially those of you involved in the > release testing. >I'm fine with an earlier branch date. If we are worried about changing the schedule, we could always keep the rc1 date the same and allow people to finish up features in the release branch during the "slow-start" period. -Tom> Cheers, > Hans > _______________________________________________ > cfe-dev mailing list > cfe-dev at lists.llvm.org > http://lists.llvm.org/cgi-bin/mailman/listinfo/cfe-dev >
Sam Kellett via llvm-dev
2017-Dec-12 11:49 UTC
[llvm-dev] [6.0.0 Release] Scheduling the release
> I see this as a positive move. As most people prepare to go into > end-of-year mode, they take less risks and commit less experimental > code. After the year begins again, people start taking more risks. The > closer we branch to the beginning of the year, they less experimental > half-backed stuff we'll carry on to the new branch and the less > reverts we'll have to do.FYI heartbleed was commited at 11pm, December 31st: https://www.quora.com/Which-OpenSSL-commit-introduced-the-Heartbleed-vulnerability
Hans Wennborg via llvm-dev
2017-Dec-14 21:56 UTC
[llvm-dev] [6.0.0 Release] Scheduling the release
On Wed, Dec 6, 2017 at 9:28 AM, Hans Wennborg <hans at chromium.org> wrote:> Hello everyone, > > It's time to start making plans for the 6.0.0 release. > > Following our regular schedule, the branch would occur about two weeks > into January, on Wednesday 17 January 2018, with the goal of shipping > early March. This is the schedule I would propose. > > However, one large consumer of the branch has asked if we could start > earlier this time, branching on 3 January instead (not moving the ship > date), to get a longer period for stabilization that syncs with their > internal process. > > While I'm hesitant to change the schedule because I think it's > important that it's predictable, there is a benefit of having large > users "in sync" with the upstream release branch, as that means more > people testing the same code. > > I will be out of the office the first weeks of January (and I'm > guessing other members of the community might be too), so while I > could get the branch started on the 3rd, it would be a kind of > "slow-start" of the process, but still allow those who want to start > testing and nominating merges to do so. > > Ultimately, it comes down to what the community prefers. Should we > stick to the regular schedule, or should we do the "slow-start" two > weeks early this time? > > Let me know what you think, especially those of you involved in the > release testing.Since there wasn't really any opposition to the 3 January "slow start" suggestion, let's go with that. I propose the following schedule: 3 January 2018 - Branch point. Those who want can start testing and nominating merges. 17 January 2018 - Release Candidate 1 tag, testing of that starts. 7 February 2018 - Release Candidate 2, things should ideally look pretty good now 21 February 2018 - Final tag. (Typically this slips a bit; just try not to slip into March.) Unless there are any objections, I'll post this on the web page soon. Cheers, Hans
Chandler Carruth via llvm-dev
2017-Dec-15 06:42 UTC
[llvm-dev] [Openmp-dev] [6.0.0 Release] Scheduling the release
FWIW, I don't have really strong objections, but I'm honestly not a fan. The reason is mostly that I think it is very late to make the change and likely to mean most people are on holiday when the branch occurs. I somewhat anticipate significantly more cherrypicks as a consequence. I'd love for Apple's releases to by sync'd with the open source ones, but I don't understand why one week earlier is so critical. That said, I generally defer to those who are working more heavily on the open source releases. The one thing I have a stronger opinion about is the idea of a "feature freeze", stabilization period, or other change. I'm pretty strongly opposed to this. One of the things that I most appreciate about the LLVM community and process is that the top-of-tree is always open, always active, and always kept green. Things that seem very likely to follow from trying to change this process: - People won't follow the guidelines because it would be a pretty huge shift from prior workflows. - We'll need some enforcement policy which will end up driving people to use more branches and generally develop things less incrementally and with less review. - There will be the feeling that outside of these windows it is some how less critical to keep top-of-tree "stable" It also isn't clear what problem this idea is trying to solve. If the release testers need the tree to start off closer to "ready", we should add continuous testing of these areas and hold patches to that *always*, not just right before a branch. Anyways, my two cents.... -Chandler PS: None of the above means we shouldn't minimize *disruption* right before a branch to make things easier. Making things hard to cherry pick, or having APIs in a half-way state isn't a great idea. But folks already do a good job (in my experience) timing disruptive changes to land in ways that are friendly to the release branching schedule. On Thu, Dec 14, 2017 at 1:57 PM Hans Wennborg via Openmp-dev < openmp-dev at lists.llvm.org> wrote:> On Wed, Dec 6, 2017 at 9:28 AM, Hans Wennborg <hans at chromium.org> wrote: > > Hello everyone, > > > > It's time to start making plans for the 6.0.0 release. > > > > Following our regular schedule, the branch would occur about two weeks > > into January, on Wednesday 17 January 2018, with the goal of shipping > > early March. This is the schedule I would propose. > > > > However, one large consumer of the branch has asked if we could start > > earlier this time, branching on 3 January instead (not moving the ship > > date), to get a longer period for stabilization that syncs with their > > internal process. > > > > While I'm hesitant to change the schedule because I think it's > > important that it's predictable, there is a benefit of having large > > users "in sync" with the upstream release branch, as that means more > > people testing the same code. > > > > I will be out of the office the first weeks of January (and I'm > > guessing other members of the community might be too), so while I > > could get the branch started on the 3rd, it would be a kind of > > "slow-start" of the process, but still allow those who want to start > > testing and nominating merges to do so. > > > > Ultimately, it comes down to what the community prefers. Should we > > stick to the regular schedule, or should we do the "slow-start" two > > weeks early this time? > > > > Let me know what you think, especially those of you involved in the > > release testing. > > Since there wasn't really any opposition to the 3 January "slow start" > suggestion, let's go with that. I propose the following schedule: > > 3 January 2018 - Branch point. Those who want can start testing and > nominating merges. > 17 January 2018 - Release Candidate 1 tag, testing of that starts. > 7 February 2018 - Release Candidate 2, things should ideally look > pretty good now > 21 February 2018 - Final tag. (Typically this slips a bit; just try > not to slip into March.) > > Unless there are any objections, I'll post this on the web page soon. > > Cheers, > Hans > _______________________________________________ > Openmp-dev mailing list > Openmp-dev at lists.llvm.org > http://lists.llvm.org/cgi-bin/mailman/listinfo/openmp-dev >-------------- next part -------------- An HTML attachment was scrubbed... URL: <http://lists.llvm.org/pipermail/llvm-dev/attachments/20171215/20b85502/attachment.html>