Displaying 20 results from an estimated 10000 matches similar to: "R-1.8.1 scheduled for November 21"
2004 Sep 06
1
First R-2.0.0 alpha version
OK folks,
We're warming up to the release of R-2.0.0 on Oct. 4 (aka 2004-10-04).
There will be two weeks of alpha releases followed by two weeks of
beta releases, starting today. The releases are made available via
CRAN in
http://cran.r-project.org/src/base-prerelease
and the first one is there already. In case of urgency or CRAN
failure, the releases will also be found at
2004 Jun 05
3
R-1.9.1 scheduled for June 21
The release of R-1.9.1 is scheduled for Monday, June 21.
Automatic generation of daily alpha releases should start Monday, June
7 and switch to beta status on Monday, June 14.
It would be good if package maintainers could get any planned changes
done as soon as possible, and test their packages carefully against
the alpha/beta releases.
--
O__ ---- Peter Dalgaard Blegdamsvej 3
2003 Nov 14
2
REMINDER R-1.8.1 beta
R-1.8.1 has now reached the beta stage with one week left before
release. This just to remind you that this would be a good time to
give the new version a spin and see whether your favourite bugs have
been cleared out.
-p
--
O__ ---- Peter Dalgaard Blegdamsvej 3
c/ /'_ --- Dept. of Biostatistics 2200 Cph. N
(*) \(*) -- University of Copenhagen Denmark
2007 Nov 18
0
2.6.1 scheduled for November 26
This is to announce that we plan to release R version 2.6.1 on Monday,
November 26, 2007.
The current experience is that beta releases receive very little end-user testing and that most bugs are not found until (shortly) after release. Accordingly, we have decided this time to skip the beta phase and go directly for one week of RC (Release Candidate) versions. The main bugs to get rid of are the
2005 Mar 02
1
R 2.1.0 scheduled for April 18
The release schedule has now been set with a release date on April 18.
The detailed procedure can be found at http://developer.r-project.org/
(it is not quite there yet, but will appear after a short propagation
delay.)
The main point for non-developers is that we start making alpha
tarballs on March 21 and beta tarballs on April 4. Only very simple
and/or critical bugs are fixed in the last
2002 Jan 24
1
R-1.4.1 scheduled for Jan 30
We plan to put out R-1.4.1 on Wednesday. This is mainly to get the
fixes that we have already made into an official version, and to clean
up the problem with the Windows build.
Several on the core team are under fairly heavy load at this time, so
we'll probably be reluctant to fix further bugs unless they are
clearly serious and/or trivial to fix.
Those of you that have unusual platforms
2002 Mar 07
1
R 1.5.0 scheduled for April 29th, feature freeze April 8
The core team has decided to release R 1.5.0 on April 29th. Somewhat
earlier than maybe expected, but we realized that we needed a
phase-shift away from our usual cycle with main releases in June and
December since it was placing feature freezes just when several
members were in a creative phase due to end of teaching.
The roadmap is as follows
April 8 feature freeze on r-base
April 15 code
2002 Jun 10
1
R-1.5.1 scheduled for Monday, June 17
As the subject says, the core team has decided to release R-1.5.1 next
Monday, mainly to "officialize" the bug fixes in the current
r-patched. It would be helpful that you check it out and report back
if you find any bad problems, especially if you have an uncommon
platform. (Or very minor nits. The intermediate ones are "out of
bounds" at this stage.)
--
O__ ---- Peter
2003 Mar 14
1
1.7.0 scheduled for April 16
We have now (actually a few days ago) declared a "Grand Feature
Freeze" on the development sourcs, meaning that we might still add
functionality and fix bugs, but we will not do any further major
changes.
It should be noted that there has been a couple of quite big changes
compared to the 1.6.x series, notably namespaces and the methods
package. Also, many more packages are now loaded
2003 Nov 21
1
R-1.8.1 is released
I've rolled up R-1.8.1.tgz a short while ago. This is a patch version
mostly fixing a number of issues in 1.8.0, some of which were quite
serious. As usual, a few new features have crept in as well. (See below
for details.)
You can get it from
http://cran.us.r-project.org/src/base/R-1.8.1.tgz
or wait for it to be mirrored at a CRAN site nearer to you. Binaries
for various platforms will
2003 Nov 21
1
R-1.8.1 is released
I've rolled up R-1.8.1.tgz a short while ago. This is a patch version
mostly fixing a number of issues in 1.8.0, some of which were quite
serious. As usual, a few new features have crept in as well. (See below
for details.)
You can get it from
http://cran.us.r-project.org/src/base/R-1.8.1.tgz
or wait for it to be mirrored at a CRAN site nearer to you. Binaries
for various platforms will
2019 Aug 15
2
Feature request: non-dropping regmatches/strextract
I do think keeping the default behavior is desirable for backwards compatibility; my suggestion is not to change default behavior but to add an optional argument that allows a different behavior. Although this can be implemented in a user-defined function, retaining empty matches facilitates programmatic use, and seems to be something that should be available in base R. It is available, for
2004 Feb 29
2
Schedule for R 1.9.0
The process leading up to the release of 1.9.0 is detailed below.
Package maintainers may want to take notice of important dates and
make sure that their packages still work with the alpha/beta releases
or work on making a 1.9.x comaptible version.
As usual, everybody is encouraged to try out the preliminary releases
and report back so that we can get the last wrinkles ironed out before
release.
2002 Oct 17
3
R-1.6.1beta available
R 1.6.1 has been scheduled for November 1.
We're makin interim beta versions available via
http://cran.us.r-project.org/src/base
(ftp://cran.us.r-project.org/pub/R/src/base used to work, but
apparently FTP access has been disabled)
The filename is R-1.6.1beta_*.tar.gz, where * is the creation date.
If you want to help ensure that the final 1.6.1 works satisfactorily
on *your* platform,
2005 May 01
0
Re: (PR#7826) ... segfault during build of 2.1.0 on RH9; print.POSIXct ...
Dear Peter,
Thank you very much for your kind and helpful reply.
As I mentioned in a followup email to r-bugs, indeed, one aspect of this
issue is a (user specified) shorter stack than that expected by R -- I
had only allowed 1 MB of stack space a long long time ago, and forgotten
about it.
Due to a glitch with r-bugs@r-project.org, I ended up submitting this
bug twice, and your original
2010 Mar 22
0
R 2.11.0 Scheduled for April 22, 2010
This is to announce that we plan to release R version 2.11.0 on Thursday,
April 22, 2010.
Those directly involved should review the generic schedule at
http://developer.r-project.org/release-checklist.html
The source tarballs will be made available daily (barring build
troubles) via
http://cran.r-project.org/src/base-prerelease/
For the R Core Team
Peter Dalgaard
--
O__ ---- Peter
2010 Mar 22
0
R 2.11.0 Scheduled for April 22, 2010
This is to announce that we plan to release R version 2.11.0 on Thursday,
April 22, 2010.
Those directly involved should review the generic schedule at
http://developer.r-project.org/release-checklist.html
The source tarballs will be made available daily (barring build
troubles) via
http://cran.r-project.org/src/base-prerelease/
For the R Core Team
Peter Dalgaard
--
O__ ---- Peter
2009 Mar 05
0
R 2.9.0 is scheduled for April 17
This is to announce that we plan to release R version 2.8.0 on Friday,
April 17, 2009.
Release procedures start Tuesday March 17. The detailed schedule can
be found on http://developer.r-project.org
The source tarballs will be made available daily (barring build
troubles) and the tarballs can be picked up at
http://cran.r-project.org/src/base-prerelease/
a little later.
Binary builds are
2009 Mar 05
0
R 2.9.0 is scheduled for April 17
This is to announce that we plan to release R version 2.8.0 on Friday,
April 17, 2009.
Release procedures start Tuesday March 17. The detailed schedule can
be found on http://developer.r-project.org
The source tarballs will be made available daily (barring build
troubles) and the tarballs can be picked up at
http://cran.r-project.org/src/base-prerelease/
a little later.
Binary builds are
2008 Jun 12
0
2.7.1 scheduled for JUNE 23
(Resent, now with correct date in subject. Doh!)
This is to announce that we plan to release R version 2.7.1 on Monday,
June 23, 2008.
Release procedures start tomorrow, Friday June 13.
The source tarballs will be made available daily (barring build
troubles) by a cron job running at 4AM CET, and the tarballs can be
picked up at
http://cran.r-project.org/src/base-prerelease/
a little later.